spot_img
HomeWeather NewsThe Wyoming Disturbance - Watts Up With That?

The Wyoming Disturbance – Watts Up With That?


Kevin Kilty

On November 13, 2025 a network outage occurred in central and northeastern Wyoming (the Northeast portion of the Western Intertie) that affected 250,000 customers, including many industrial customers. Some of these were without power for up to 10.5 hours. The North American Electrical Reliability Council (NERC) and Western Electric Coordinating Council (WECC) have released a report on this major event, and a hearing about was scheduled to take place at the Wyoming Public Service Commission on Wednesday July 15, 2026, but has now been postposed until August 7.

I have read the 49 page report, reports that it references, and I have collected additional information, or what I could collect from EIA, in order to be informed to some degree before the meeting, which I plan to attend.  The event was complex to say the least.

Timeline of the Disturbance

In what follows I often refer to voltage at a substation, but I intend this to also mean voltage on the electrical “bus” that this substation serves.

I think what can be established about this event is that it involved a long sequence of blunders some of which were latent errors in the system since the inauguration of some parts of the supervisory data network in 2020. There are a few mysterious items in its description that I hope to have cleared up by the end of the hearing in August.

The proximal cause of the outage was a scheduled disconnect of a 500kV transmission line in Central Wyoming, Aeolus near Medicine Bow, to Clover near Mona Utah, which generally carries wind generated power when such is available, or thermal power when needed. This is a new transmission line (Gateway South) which was advertised in its Wyoming PSC application for necessity and public convenience as a way to move wind energy out of Wyoming. Wyoming has far more wind generation at times than it can possibly use. The nature of this planned outage was to replace/decommission some reactors, the series compensation for Aeolus-Clover, at several electrical substations along its path.

The outage was scheduled for 8 am on November 13, but was delayed until 12:43 because needed personnel were not available at a substation in southern Wyoming (Little Snake on the Colorado/Wyoming border) and noon became a new targeted time instead. The Southwest Power Pool (SPP) as it turns out had planned with the Western Area Power Administration (WACM) to shutdown another area transmission line in the area and was informed they could begin this during the delay period of shutting down Aeolus-Clover. As the scheduled time for Aeolus-Clover shut down approached, SPP became concerned about excess grid energy from wind generation. A number of transmission lines in the area were already down since November 12 for reasons of maintenance and SPP became concerned that rising wind power and solar would present problems for grid stability.

Updated plans made at this point (late morning on November 13), involved discussion among a number of reliability coordinating entities, and it was first determined that PACE would need to curtail 820MW of wind energy to avoid excess energy in the bulk electrical system in the area.

While it would seem that adequate planning ahead of time had alerted everyone about what to expect. What actually occurred was a surprise. Schedules were constantly changing and a communications outage was preventing PACE from fully measuring the state of its network in southern Utah. Discussions among all entities resulted in RCW and PACE agreeing to curtail only 200MW of wind generation, rather than 820MW planned earlier. At this point PACE (and SPP too) felt that the system was clear to remove Aeolus-Clover, but RCW had not yet assented to the shutdown – a case of miscommunication.

In a mistake reminiscent of the 2003 blackout in the northeastern US and southern Canada, low voltage alarms in the PACE network had never been enabled since their installation, and PACE didn’t realize their substation at Aeolus was already near a low voltage limit.[1]

Moreover, even though PACE had modeled their network state with Aeolus-Clover shut down, the modeling parameters for various generators were not physically possible. In other words, PACE had a valid solution to a model giving them confidence to proceed shutting down the transmission line, but not a physically viable one.

Upon shutting down Aeolus-Clover at 12:43, there was now deficient power available to parts of the network rather than the worry of SPP that there would be too much power. According to the report, at the moment of shutting down Aeolus-Clover a cascading failure began…

“This cascading was due to a shift of flows onto the Aeolus–Anticline line, which caused the local voltage to collapse to 138 kV (~0.28 pu)…”

I am unsure if the authors of the report are using the word “onto” in the manner I would understand clearly. I would think that phrase would indicate power that had been flowing on Aeolus to Clover now switched to Aeolus to Anticline. Yet, this makes the collapse of voltage difficult to see as flows into the remaining transmission line would cause voltages too high instead.

The Aeolus-Anticline (anticline substation is near Jim Bridger Power Station east of Rock Springs, Wyoming) voltage dropped to 28% of its nominal operating value in 344mSec which opened its circuit breakers. In turn, the substation at Windstar, northwest of Glenrock, Wyoming which was already in a precarious voltage state unknown to network operators, saw its voltage decline to 23% of nominal operation in another 279mSec and it disconnected. By this time thirteen other transmission lines disconnected. Northeastern Wyoming and western South Dakota became an electrical island which then collapsed completely in another six (6) seconds.

By the end of those six seconds the grid lost  1,140MW of load, 4,800MW of generation, 33 bulk electrical system transmission lines, and 250,000 customers.

All four units of the Dave Johnson power station near Glenrock disconnected, and the chaos and guessing about network state that followed for a time allowed power at low voltage to be reconnected to Unit Four of Dave Johnson. Unfortunately this voltage was below the voltage alarm limit that would prevent the generator of Unit Four from entering a motoring mode (generator operating as a motor rather than a generator). This did quite a lot of damage and Unit Four is still offline eight months later.

Restoring power

Restoration of power proceeded slowly because operators had incomplete knowledge of their network state. In such a condition their first step should have been to assess and verify the network state before trying to restore power. Instead there was some guessing which led to mistakes. Re-energizing transmission lines without knowing the full state of the network was a major problem. I think the damage to Dave Johnson unit four was part of this.

A lesson drawn so far from this episode is that while operators had been trained in restoring a completely black grid, they were not trained for this partial blackout. There were also deficiencies in the supervisory data system, including some of SPPs data acquisition and supervisory system dropping out at 12:20 well before the outage. It wasn’t until SPP organized a conference call at 14:16 that the full state of the network was recognized, and restoration of power began to proceed productively.

Puzzling things I hope to learn about at the PSC

There are several statements made in this report that I would like to see validated.

First, I find it odd that while everyone concerned saw the potential problem as too much energy in the networks once Aeolus-Clover was disconnected, it seems the opposite occurred – voltages collapsed at first. Maybe this is explained by simulations ahead of time using incorrect parameters, or that each entity had an unclear picture of the network of others, or that communications prevented both PACE and WAMC from having a complete picture of their networks.

Second is this, while the report focuses on recovery efforts and mistakes made there, there is no real explanation of what caused the cascading failure in the first place. Was there a disturbance propagated across the grid that caused Inverter Based Resources (IBR) to fail a “ride through“ of the disturbance. Failure to ride through had been observed four times in 2024 in the Western area, one of which occurred in PACE. An example of failure to ride through is shown here in Figure 1 from the report of those earlier failures.

Figure 1.

These earlier IBR failures were related to the inverters involved not being set to maximum capability to ride-through. So, one would think that advice having gone out to all resources about this problem would have prevented it from occurring in November 2025.

Instead, PACE claimed that

“… IBRs supported a faster frequency recovery across the interconnection, driven largely by battery energy storage systems, while wind generation provided readily available capacity during system restoration…”

And made this orphaned claim

“PACE identified that the ability to use wind resources helped it restore the system…”

Almost 5,000 MW of generation was lost, and it took many hours to restore power. I am doubtful that there is enough battery storage in this area to have aided much. After all, the region is rich in coal and gas-fired power to backup wind/solar. PACE’s Integrated Resource Plan (IRP) indicates plans to add battery storage, but not that it has been installed as yet.

There is a suggestion in the report that the mix of resources available at the time provided frequency support to the tune of 2,800MW per 0.1Hz which is far greater than the Frequency Support Obligation required. I would like to know what parts of the mix were valuable for this frequency support as the report indicates that the grid was short of inertia and reactive power.[2]

Figure 2. Generation by source in PACE. The red arrow indicates time of the Wyoming event.

As far as wind resources aiding the recovery I refer to Figure 2 nearby, which shows generating data from PACE. It indicates that wind energy rose substantially in the two hours before the outage. I’d like to know the origin of this wind energy, but I’ll simply note that it occurs coincident in time with the RCs and SPP negotiating with PACE about curtailing 820MW of wind. Could it be that estimates of the needed curtailment were complicated by this sudden ramping of wind energy?

Figure 3 is a close-up of a spreadsheet I put together from EIA data from the relevant time period. Note that I have added columns that are labelled with a “Delta”. These show the change in the category of generation from the previous hour. The “Delta Wind” column shows a drop of 816MW in the hour the outage began which is suggestive of the 820MW that SPP advised would be prudent. However, the RCW and PACE were ultimately speaking about only 200MW. Maybe I’ll get an explanation of this.

The sudden loss of 816MW of wind in the final 17 minutes of hour 12pm to 1 pm, suggests a sudden loss of 3,000MW of wind at about 12:43 that persisted through the next hour. Indeed, the 1pm to 2 pm hour shows a loss of an additional  2,200MW, making a total loss of 3,000MW hours at 12:43.

Figure 3. Spreadsheet of EIA data from PACE balancing area. I have added columns labelled “Delta” to show changes from the previous hour.

Then note in the column labelled “Delta Firm PACE”, which combines the two firm power sources in PACE, coal and natural gas, that these firm sources were being scaled back to accommodate rising solar and wind, just like a normal day. Solar energy is generated in PACE largely in southwest Utah, and I might justifiably suspect the following. Was solar power from Southern Utah flowing toward Aeolus on the Gateway South transmission line at the time of the cascading failure? PACE admitted that they were having trouble getting a full picture of network state in Utah, but they assured the RCW that “they didn’t need to shift power around much.”

Something I have never had clarified about Gateway South is this.

When Gateway South was pitched originally it was to aid moving wind energy out of Wyoming, but a letter I sent to the Office of Consumer advocate pointed out that there was two-way metering intended at the Colorado/Wyoming border and this line could convey curtailed solar from Utah, complicating Wyoming hopes for selling wind and coal. Maybe solar power was flowing toward Aeolus at 12:43 and opening that line caused the sudden decline in voltage. Maybe?

Note also that wind was added back into the PACE balancing area in wimpy amounts totaling only a few hundred megawatts by 6pm on the 13th. In contrast the “Delta PACE firm” column shows 2,500MW of firm power was added back over the same period. So, while it is true that “wind power helped restore the grid”, firm power did more. It also helped to cut exporting power to Idaho Power Company by 800MW as Figure 3 also shows. In fact

Finally, wind would likely have been ineffective late in the day on November 13 anyway, as I assume it was declining in intensity toward evening. I have no direct measure of available wind in PACE because of the chaos, but Figure 4 is a plot of Public Service Company of Colorado generating sources, and one will see that wind disappears in eastern Colorado just when efforts to restore power in Wyoming and the Dakotas are in full swing. Wind energy in PACE is pretty highly correlated to wind in Eastern Colorado. PacifiCorp is a very wind/solar supportive utility. Is all the talk of wind and batteries aiding true, or just protecting the reputation of renewables?

I await August 7 to find out.

Notes: 1-The 2003 outage I refer to was the result of a network solver program that was updated early in the day, but then had failed to be restarted, giving operators at a utility in Ohio faulty network state information.  When operators restarted the solver nine minutes before this cascading blackout, it reported a network state so at odds with normal experience, the operators at first doubted it.

2-This statement is reminiscent of the Spanish blackout in 2025.

Glossary of Abbreviations to aid anyone trying to read the report.

BES – Bulk Electrical System

BHE – Black Hills Energy

IBR – Inverter Based Resources (wind/solar or battery direct current (DC) resources connected through an inverter that makes AC for connection to the network)

PACE – PacifiCorp East balancing area

PU (pu) – per unit measure. Used instead of actual units because of the variety of voltages used in a network. So, voltage dropping to 0.28pu, means dropping to 28% of nominal operation.

RAS – Remedial Action Scheme

RC – reliability coordinator

RCW – Reliability coordination west

RTCA – Real Time Contingency Analysis

SPP – Southwest Power Pool

TSGT – TriState Generation and Transmission

TOP – Transmission operators

UFLS – Under Frequency Load Shed

WACM – Western Area Power Administration, Colorado Missouri balancing area (Note: Since WACM joined with SPP in April, I am no longer able to fetch EIA data for this entity. Its November data may still exist, but I haven’t found it.)





Source link

RELATED ARTICLES

Most Popular

Recent Comments